In other school construction news, at a special meeting Tuesday, March 26, the State College Area School District Board of Directors approved construction bids for the South Building totaling $11,656,900, the base bids were awarded to:

  • Leonard S. Fiore, general contractor, $9,284,000
  • Silvertip, Inc., plumbing and fire prevention, $896,000
  • Silvertip, Inc., HVAC, $579,600
  • Bob Biter Electric, electric, $897,300

In addition, the project will require an estimated $2,505,585 in soft costs for such expenses as permits, testing, fees and a contingency fund.
The total project costs (construction plus soft costs): $14,322,485